M4/M48 Toll Booth Removal

M4/M48 Toll Booth Removal


Bath Demolition were awarded the contract to demolish and remove the M4/M48 Toll Booths. The work was planned in phases in order to minimise the impact on traffic.

High traffic levels meant the project was granted total road closure overnight for demolition works to be carried out. An hour-by-hour program of works, extra resources and plant were all put in place to cover all eventualities. With a highly anticipated and nationally televised opening of the new toll-free road, it was imperative that all phases of work were completed on time and to budget.

Separation of the canopy was carried out by use of MEWPs with a Hot Works Permit in place, and removal by mechanical methods using 360 Excavator with a shear attachment. The remaining structures were demolished using 360 Excavator.

M4/M48 Toll Removal Process

Completion: April 2019

Duration: Phased over 4 weeks

Testimonials

Matt, Barnie, Mick & George were especially polite and courteous.

Make Group

I would have no hesitation in recommending them having worked with them for over a decade on various projects.

Sir Robert McAlpine

An excellent response to an emergency situation. Works undertaken promptly and professionally.

Steinhoff Property Group

Very professional service provided.

Redrow Homes

They are attentive, friendly, non-combative, and will more often than not avoid costly variations to only claim up to the value of their order to ensure that you keep on budget. I would recommend this contractor to any potential customer.

Bellway Homes

Dear Bath Demolition,
Just wanted to say a quick thanks very much. We have been working on your school site down in Newton abbot for the last week clearing the trees. A very well organised, safe site and your guys couldn't of been more helpful, well worth a mention and thank you. A credit to you! If only all sites were like this!

Simon Hart, Director - Hartwood Timberworks Ltd

On behalf of the Hospital Company (Southmead) Limited, I am writing to thank you and your team for your role in completing the Southmead Hospital Redevelopment Project. Your contribution and determination to support the completion of this project, which started in 2010 and was completed in June of this year (2019), is recognised. Without your support this momentous milestone could not have been achieved.

Hospital Company (Southmead) Limited

Accreditation
Accreditation
Accreditation
Accreditation
Accreditation
Accreditation

Based in Bristol, Bath Demolition carries out demolition and site clearance nationwide.

Get in touch

Aldermoor Way,
Longwell Green,
Bristol, BS30 7EU

T: 01179 600 000
E: enquiries@bath-demolition.co.uk