Cadbury’s

Cadbury's Somerdale Factory, Keynsham


Bath Demolition were awarded the contract for the separation and demolition of D block at the former Cadbury’s Somerdale Factory Located in Keynsham.

The redundant 3 storey structure was of a steel frame construction with brick panel infill, the intermediate floors and roof were reinforced concrete, above existing ground level with a further partial 2-storey basement.

Following the demolition of the main structures utilising our high reach demolition machinery the basement void was propped and backfilled with the site won crushed demolition material. 100% of the demolished structure was either successfully reused on site or recycled.

Cadbury's demolition project

Completed: February 2014

Programme: 18 weeks

Accreditation
Accreditation
Accreditation
Accreditation
Accreditation
Accreditation
Accreditation
Accreditation
Accreditation

Based in Bristol, Bath Demolition carries out demolition and site clearance nationwide.

Get in touch

Aldermoor Way,
Longwell Green,
Bristol, BS30 7EU

T: 01179 600 000
E: enquiries@bath-demolition.co.uk