Baldwin Street

Baldwin Street, Bristol


Bath Demolition carried out a large demolition and enabling works package in the centre of Bristol.

The scope included:
Internal demolition of the building to leave only external and party walls standing
Temporary retention of the façade with RMD Super slims
Removal of remaining asbestos
Permanent piling and erection of four permanent steel frame towers to act as support to the external and party walls thus mitigating the need for a large amount of temporary works
Installation of crane base and erection of tower crane

To carry the works out safely, a large 10,000 cubic meter birdcage scaffold was installed, which needed to be adapted as the works progressed. A Tower Crane and base was also installed to assist with the demolition works.
Much of the demolition was carried out by hand and a remote controlled Brokk Excavator was used wherever possible.

The project was delivered on time and within scope of the contract.

Baldwin Street

Completion: October 2019

Duration: 7 months

Testimonials

Matt, Barnie, Mick & George were especially polite and courteous.

Make Group - Bristol

I would have no hesitation in recommending them having worked with them for over a decade on various projects.

Sir Robert McAlpine - Hertfordshire

An excellent response to an emergency situation. Works undertaken promptly and professionally.

Steinhoff Property Group - Birmingham

Very professional service provided.

Redrow Homes - Bristol

They are attentive, friendly, non-combative, and will more often than not avoid costly variations to only claim up to the value of their order to ensure that you keep on budget. I would recommend this contractor to any potential customer.

Bellway Homes - Cardiff

Dear Bath Demolition,
Just wanted to say a quick thanks very much. We have been working on your school site down in Newton abbot for the last week clearing the trees. A very well organised, safe site and your guys couldn't of been more helpful, well worth a mention and thank you. A credit to you! If only all sites were like this!

Hartwood Timberworks Ltd - Exeter

On behalf of the Hospital Company (Southmead) Limited, I am writing to thank you and your team for your role in completing the Southmead Hospital Redevelopment Project. Your contribution and determination to support the completion of this project, which started in 2010 and was completed in June of this year (2019), is recognised. Without your support this momentous milestone could not have been achieved.

Hospital Company (Southmead) Limited - Kent

Accreditation
Accreditation
Accreditation
Accreditation
Accreditation
Accreditation

Based in Bristol, Bath Demolition carries out demolition and site clearance nationwide.

Get in touch

Aldermoor Way,
Longwell Green,
Bristol, BS30 7EU

T: 01179 600 000
E: enquiries@bath-demolition.co.uk